Most contractors run out of cash before Phase 1 is over. Here's why.
And no, it doesn't always mean they priced the project badly.
Sometimes, the project is profitable on paper, but the money is leaving faster than it's coming in.
Picture this.
You've secured a construction contract. Work begins. You mobilise workers, hire equipment, buy materials and prepare the site.
The expenses start immediately.
But the client's money?
Still being processed.
Here are four things that create the cash flow squeeze.
- You finance mobilisation yourself.
Before the first payment comes in, you've already spent money on labour, materials, transport and site setup.
You're effectively financing the project out of your own pocket.
- Your first payment takes longer than expected.
You've completed measurable work and submitted your payment certificate.
But it still needs review, verification and approval.
Meanwhile, workers need paying and suppliers are following up.
- Retention reduces what you receive.
Even after approval, the client may withhold a portion of your payment as retention.
So, the amount you receive is less than the value of the work you've completed.
- Phase 2 doesn't wait for Phase 1 money.
You still need to buy materials, maintain labour and keep the site moving.
Now you're funding the next phase while waiting to recover money spent on the previous one.
And that's how a seemingly profitable project becomes a cash flow headache.
So, what can you do before mobilisation?
- Prepare a 13-week cash flow forecast. Map expected receipts against actual payment obligations.
- Negotiate a mobilisation advance where the contract allows.
- Submit payment certificates promptly once the work is measurable.
- Track retention separately so you know what's withheld and when it's due.
- Negotiate supplier terms that align with your expected client payment cycle.
One thing to remember:
A contract can make a profit and still run out of cash.
Before asking how much you'll make from a project, ask yourself:
How much money will I need to keep this project running before the client pays me?
That answer could save your project.